Power sector uncertainty and debt trap

From dependence on domestic gas, we have now become heavily dependent on imported liquefied natural gas. It is said that we are doing this to address the gas shortage because of the dwindling domestic reserves. We have assumed that the power demand by 2030 will roughly be 34GW and to meet this, the government has set a target of achieving 10GW of LNG-based capacity.

But, the question is: is our economy ready to ensure the supply of this import-dependent product? Will we be able to provide the foreign exchange? Is the electricity demand that has been determined by 2030 reasonable? By 2026, our peak demand was 17GW. Will our demand double in four years? Or are we opening all avenues to provide benefits for special business groups by determining the additional demand?

Importing liquefied natural gas means building a huge infrastructure for it. This oil is imported by sea which requires a large infrastructure for unloading, storing and converting it into gas. About 30 per cent of the total demand for gas is processed in the floating storage and re-gasification unit anchored off the coast of the Maheshkhali island. There are two terminals: Maheshkhali floating LNG with a capacity of 600mmcfd is operated by US-based Excelerate Energy. This terminal, launched in August 2018, has a contract for 15 years. The second is the Summit LNG Terminal. The Summit Group also operates it through Excelerate Energy. This terminal, with a capacity of 500–550mmcfd, was launched in April 2019. This is also contracted for 15 years.

This offshore supply system feeds the Meghnaghat hub, which is home to several power generating plants. This is where 718MW Reliance Meghnaghat, 584MW Unique Meghnaghat and 583MW Summit Meghnaghat 2 power plants are located. The plants depend on a narrow offshore supply system located a few hundred kilometres away in the cyclone-prone island of Maheshkhali.

The government plans to build five liquefied natural gas terminals by 2035 to boost gas supplies for industrialisation as domestic natural gas production declines rapidly. The planned facilities are composed of three floating storage and re-gasification units and two land-based terminals. One of the three planned floating storage and re-gasification units will be located at Kutubjom, in deep water off Maheshkhali in Cox’s Bazar, under a government-to-government proposition by a Chinese company. The cabinet committee on economic affairs gave the policy approval on July 28 to the proposal. The terminal is expected to start supplying re-gasified liquefied natural gas by mid-2028, potentially adding 600mmcfd to the re-gasification capacity. The government expects to sign a deal for another floating storage and re-gasification unit of a similar size by December 2026. It examines the feasibility of urgently setting up at least one more floating storage and re-gasification unit in the south-west or near Payra or Mongla port. Of the two planned land-based terminals, state-run Petrobangla is working to develop a 7.5 million tonnes per annum facility near the under-construction Matarbari deep-sea port in Cox’s Bazar.

We know that there is a need for an ‘energy highway’ operated by the Gas Transmission Company Ltd to transport power from the coast to industrial areas. This network is required to ensure a stable supply, but it will have to overcome significant engineering and financial constraints.

Now, the gas from the floating storage and re-gasification unit goes to the Maheshkhali zero point. This section is connected by the 30-inch Maheshkhali–Anowara line, with a capacity of 500mmcfd, and a parallel 42-inch line, with a capacity of 1,200mmcfd, commissioned in 2021, which will easily deliver gas to the land. Another 181km 36-inch south-east arterial line connects the Anowara city gas station to the Bakhrabad hub. Advanced horizontal directional drilling methods were required in this section to avoid crossing four major rivers. In addition, a 50km 42-inch loop spanning Bakhrabad, Meghnaghat and Haripur, called the dedicated power supply link, supplies high-pressure feed to six power plants. To handle the huge flow, the company uses automated town border stations and telemetry infrastructure at Mirsarai and Bakhrabad to adjust the transmission pressure to the plant demand. The 295km Maheshkhali–Bakhrabad extension line is being built for $1.4 billion by 2029. It aims to supply 1,800mmcfd of gas. While the pipelines will increase physical flow, they will put the national exchequer in a delicate position.

In fact, to build this supply infrastructure, we will have to meet huge import bills. This could put the revenue system at risk. If LNG consumption increases by more than 60 per cent after 2030, the risk will increase even more because of the rise in the dollar price or the depreciation of the taka and the shock of global inflation. Under the base cost scenario of $12 per million British thermal unit according to the Brent index, the annual bill is about $8.5 billion. However, a volatility shock of $20 per million British thermal unit could push this bill to $14 billion.

We are already burdened with foreign debt. According to recent data, Bangladesh’s total foreign debt is about $113.51 billion. A large part of the national budget, about 10 to 15 per cent or more, goes to interest and principal repayments on debt. This amounts to crores of takas. Already, the main expenditure of the national budget is paying off foreign debt. An estimated $30–45 billion will be needed to ensure LNG supply between 2026 and 2050, depleting reserves and exacerbating the debt crisis. Again, the government buys liquefied natural gas for Tk 50 per cubic metre and sells it for Tk 30–31.50. The government will have to increase electric prices to close the gap, raising concerns about how long this situation can continue, which will create the risk of social and industrial instability. Petrobangla’s increasing reliance on foreign debt and international payment guarantees to pay import duties shows all the signs of being entangled in a long-term debt trap. Are we knowingly getting into this debt trap to benefit a handful of business groups?

This infrastructure, especially the offshore floating storage and re-gasification units in the Bay of Bengal, becomes quite vulnerable during the monsoon seasons. A single technical fault or storm can stop re-gasification, resulting in immediate and widespread power outage. We saw this in August. Again, high energy prices may force the government to reduce import, which will result in the terminals performing lower than their production capacity, which means that plants costing billions of dollars will remain idle while independent power producers will keep getting paid capacity charge. So, even if electricity is not generated, money will continue to flow out of the treasury.

However, we could have focused more on expanding the renewable energy sector without increasing dependence on liquefied natural gas. We are not even paying due attention to the target for expanding renewable energy, which is to generate 10GW by 2030. We could have made families self-sufficient in power by encouraging them to install solar panels on their roofs. Recently, a proposal has been made by way of which the government will buy power for three years as an incentive for the establishment of solar panels. We guarantee purchase of electricity from independent power producers throughout the year. We keep paying the power producers even if they do not produce power. If we can give benefits to rich and big business entrepreneurs and if we can give them subsidies, why cannot we give such benefits or subsidies to small, family entrepreneurs and ordinary people! Why is there so much neglect for small or marginalised people? Will the government benefit only the rich and businessmen?